01Free Property
Check & QuoteStart here
- On-site visit and feasibility study to confirm your Colorado
lot.
- Zoning, setbacks, floodplain, and solar-shadow analysis for
your local jurisdiction.
- Site plan, interior and exterior renders, and floorplans.
- Estimated budget with financing options.
02Contract,
Pre-Permit Planning & Approval3–5 months
- Two contracts: a preliminary planning agreement, then a
fixed-price build agreement.
- ISP survey, soils report, and foundation design.
- Architectural and structural engineering drawings.
- Permit submission handled for you — Boulder, Denver,
and jurisdictions across Colorado.
03Manufacturing2–3 months
- Steel frame with mechanical, electrical, and plumbing.
- Drywall, flooring, cabinetry, and fixtures — finished
indoors to 90%.
- 200+ quality-control checks.
- State-inspected for quality and code compliance.
04Pre-Delivery
Site Work & Shipping1–2 months
- Excavation, underground utilities, and a helical-pile or
concrete foundation — run in parallel with the build.
- Fully insured, monitored transport to your site.
05Installation
& Final Completion1–2 months
- One-day crane placement onto the foundation.
- Matelines closed, roof set, utilities connected, and
landscaping.
- Final inspection and adjustments to Olerra's standards.